Understanding your building project timeline helps you plan better and avoid frustration. Here’s what actually affects how long your building project will take from start to finish.
One of the most common questions we get at Jakaan Architects is: “How long will my project take?” It’s a fair question, but the answer depends on several factors that many people don’t initially consider, particularly around the council approval and development application process.
The truth is, there are different approval pathways, potential delays, and variables that can significantly impact your project timeline. Let’s break down what you can realistically expect and what might affect your project schedule.
The Two Main Approval Pathways
The timeline for your project largely depends on which council approval pathway is available for your site. While a Complying Development Certificate (CDC) is generally our preferred pathway because it can be faster and more predictable, it isn’t available for every property. Factors such as bushfire risk, flooding, heritage value, biodiversity and land zoning can mean a project needs to follow the Development Application (DA) and Construction Certificate (CC) pathway instead.
At the beginning of a project, we organise a site survey and obtain a Section 10.7 Planning Certificate from the local council. Together, these help us understand the planning controls and constraints that apply to the property and whether CDC may be an option.
Development Application + Construction Certificate
A Development Application (DA) and Construction Certificate (CC) is the traditional two-part approval process in New South Wales. Here’s what you need to know:
The Legal Framework: A development application is deemed refused after 40 days if council hasn’t made a decision. This doesn’t mean you’ve been rejected – it means you have the right to take your application to the NSW Land and Environment Court for a determination.
Reality Check: While developers sometimes use this 40-day rule to pressure councils, most homeowners don’t want to go to court. The average approval time in NSW is actually 108 days – that’s roughly 3-4 months.
Our Experience: We always tell clients to expect 6-9 months for a DA approval. This might sound pessimistic, but if it happens faster, you’re ahead of schedule. If there’s any complication – neighbour objections, additional department referrals, or site complexities – it can easily stretch to 9 months or even 18 months.
Our Folding House sits on a sandstone escarpment above the Blue Mountains National Park, with a Flame Zone bushfire rating. A site like this needed the DA and CC pathway, with bushfire consultant input built into the design from day one.
Best Case Scenario: We’ve had a development application for a house on a flat block with no bushfire constraints approved in three weeks. But this is exceptional – everything went perfectly with no complications.

Complying Development Certificate (CDC)
Where a property and proposed development meet the requirements, a Complying Development Certificate (CDC) can provide a faster, more streamlined process by combining planning and construction approval in one process. However, not every site is eligible for CDC.
How It Works: Your application goes to a private certifier rather than council. They review it, provide a list of required changes, and once those are addressed, approval typically comes within a week.
Realistic Timeline: In our experience, a CDC takes 1-3 months from initial submission to approval. There’s usually some back-and-forth to tick all the boxes and ensure everyone understands the plans, but it’s much more predictable than the DA process.
Our recent Monica Place project was able to use the CDC pathway. The project went from initial enquiry in early 2024 to CDC approval in September 2024, with construction completing in July 2025. The total project timeline was under two years from first contact to move-in.
The Advantage: When a CDC is available, it can significantly reduce the time spent in the approval process compared with a traditional DA and CC. However, CDC generally applies to more straightforward sites and projects that can meet its more conservative set of planning rules.
Properties affected by significant bushfire risk, flooding, heritage value, biodiversity requirements or certain land zoning may not qualify. This is why establishing the site’s planning constraints at the beginning of the design process is so important.

What Can Slow Things Down
Council-Related Delays
Several factors can extend your approval timeline:
- Neighbour Notifications: If your project requires neighbour notification and someone objects, this slows the process down significantly.
- Department Referrals: Complex sites might need input from multiple departments – bushfire, water and land conservation, heritage, or environmental agencies. Each referral adds time as these departments aren’t part of council and work on their own schedules.
Construction Phase Delays
Once you have approval and start building, other factors come into play:
Weather: Under any building contract, if there’s a day when the builder can’t work due to rain – whether they’re laying concrete, doing framing, or working without a roof – time gets legally added to the contract. This is standard and protects both you and your builder.
Materials and Supply: Material availability can occasionally affect a construction program, particularly if a selected product has a long lead time or becomes unavailable. This is generally managed by the builder during construction, with materials and finishes refined between the architect, client and builder to suit the design, budget and project requirements.
Decision-Making: It’s crucial that you, as the client, make decisions and answer questions as efficiently as possible. Under building contracts, if you don’t respond promptly to requests for decisions, the builder has legal grounds to extend the contract timeline. Standard building contracts, as outlined by the Master Builders Association NSW, include provisions for these extensions to protect both parties.

Regional Considerations
Working across the Blue Mountains, Penrith, and Hawkesbury regions, we see how local factors affect timelines:
- Heritage Considerations: Blue Mountains heritage listings or buildings with heritage value can add complexity and time to the approval process and will generally require the DA/CC pathway rather than CDC.
- Bushfire Zones: Many properties, particularly across the Blue Mountains, are affected by bushfire planning requirements, which involve additional consultants and department referrals. See how we approached this at Faulconbridge House. Where the bushfire risk is significant, this can rule out CDC and mean the project needs to proceed through the DA/CC pathway, with additional assessments or consultants potentially required.
- Flood-Affected Land: Properties affected by flooding, including sites around the Nepean River, may also be excluded from the CDC pathway and require a DA/CC.
- Site Access: Some Blue Mountains locations have challenging access that can affect construction timelines, especially during wet weather.
How to Minimise Delays
During Design and Approval
Understand Your Site Early: One of the first things we do is organise a site survey and obtain a Section 10.7 Planning Certificate from the local council. This helps identify the planning controls and constraints that apply to your property, including zoning, bushfire risk, flooding, heritage and biodiversity.
Choose the Right Approval Pathway: Not every project or property is eligible for a CDC. Once we understand the site’s constraints, we can determine whether CDC may be possible or whether the project will need to follow the DA/CC process. CDC typically has a more conservative set of rules, so if it is an option, we can design with those requirements in mind from the beginning.
Plan the Design Around the Requirements: Understanding the approval pathway early means we know which rules we need to follow as the design develops. This reduces the risk of designing something that later needs significant changes to gain approval, helping to avoid unnecessary delays.
Quality Documentation: Good documentation by a registered architect enhances your project’s chances of smooth approval. Clear, compliant drawings reduce the back-and-forth with certifiers or council.
During Construction
- Material Selection: During construction, the builder will manage ordering, lead times and availability. Where a selected material or product creates an issue, we can work with the client and builder to consider suitable alternatives while protecting the overall design intent and keeping the client’s budget in mind.
- Clear Communication: Establishing good communication protocols with your builder and making decisions promptly keeps projects moving.
- Realistic Expectations: Understanding that weather delays and minor supply issues are normal helps manage expectations and reduces stress.
The Value of Experience
Our decade-plus experience working with local councils and understanding regional planning controls means we can often predict and avoid common delays. We know which councils move quickly, what documentation they prefer, and how to structure applications for the best chance of smooth approval.
Setting Realistic Expectations
Here’s our honest advice on timelines:
For DA Projects: Plan for 6-9 months approval, then add your construction time. Complex sites or unusual requirements can extend this significantly.
For CDC Projects: Where your site and project are eligible for CDC, plan for around 1-3 months from submission to approval, followed by construction. This pathway is generally much more predictable than a DA/CC.
Construction Phase: Add 10-20% buffer time for weather, supply issues, and minor complications. It’s better to be pleasantly surprised than constantly stressed about delays.
Communication Is Key
Throughout the process, we keep you informed about progress, potential delays, and realistic timelines. Good project management means no surprises – you’ll know what’s happening and when to expect the next milestone.
Whether you’re planning a residential renovation, new home, or commercial project, understanding these timeline realities helps you plan better and reduces frustration during the process. For large-scale developments, take a look at our urban planning projects to see our approach and experience in more detail.
Browse our completed projects to see how these approval pathways play out on real sites.
Ready to discuss your project?
Contact our team for an honest conversation about your project scope and realistic timeline.
We believe in setting realistic expectations and managing project timelines through careful planning and experienced project management.